Our Omnivex SCADA project has around 1,500 tags. The server's disk is almost full and our IT department found that the database has grown to about 180 GB in one year. Reports with longer time ranges have also become slow.
When the project was created, I think most tags were simply set to periodic logging with the same short interval. I don't want to lose important history, but clearly we log far more than we need. How should I review the log settings, and what values make sense for different types of signals?
When the project was created, I think most tags were simply set to periodic logging with the same short interval. I don't want to lose important history, but clearly we log far more than we need. How should I review the log settings, and what values make sense for different types of signals?
Comment